*Determination, construction and signalization of the location of the 3th order ground control points (C3) according to the flight plan. (56 pc)
* Determination, construction and signalization of the location of the 3th order ground control points (C3) according to the flight plan. (56 pc)
* Carrying out GPS Static Measurements of All Ground Control Points (C3 & C4) and concluding the calculations
* Carrying out Geometric Levelling Measurements of All Ground Control Points (C3 & C4) and concluding the calculations
* Carrying out GPS RTK measurements of road platform along the highway which is 57 km and delivering the cad drawings
* Preparations of Calculation Reports, Ground Control Description Cards to be approved by General Directorate of Land Registry and Cadastre (TKGM)